Lismore Airport Terminal
August 2024 update
At the Lismore Regional Airport, substantial structural developments were noted with the ongoing installation of the Porte Cochere's structural steel. Excavation activities for new grounds lighting progressed, alongside the removal of old carpark lights to a storage area, making way for modern infrastructure. Earthworks continued with trenching for lighting footings and silt fencing containment. The airport's carpark civil works were a focal point, culminating in the completion of new kerb and gutter installations and the addition of Porte Cochere roof flashings by the end of August.
July 2024 update
At the Lismore Regional Airport, work is progressing on several fronts.
The Porte Cochere roof soffit has been removed and abrasive blasting of the structural steel is underway. Additionally, the old structural steel is being replaced with new roof purlins.
Power systems have been updated and the plans and approvals for Stage 2 are almost complete.
Excavation and electrical work for upgrading the car park lighting are also ongoing.
May 2024 update
Stage 2 commenced in May 2024, with terminal upgrades externally. Scope of works includes front entry and fly over roof. Electrical upgrades and carpark repairs have now also been approved.