Lismore City Hall

August 2024 update

City Hall experienced a series of enabling works, but progress has been curtailed due to funding constraints. Despite the site's demobilization, detailed designs and a comprehensive cost plan for its restoration and improvement have been completed and received. Council is working with various State Government funding agencies to commence Stage 2 (construction and refurbishment) as soon as possible.

July 2024 update

Early works at the Lismore City Hall site included completing Stage 1 footings and blockwork, which were core-filled.

The setup of stage 2 footings, columns and block walls, along with the installation of structural beams, progressed.

Adjustments to props allowed for the next stages of work, with blockwork and column installations completed by late June.

Stage 1 has been successfully completed, with preparations underway for the initiation of Stage 2.

Work at city hall.

May 2024 update

Asbestos removal (windows) to the western façade and the north elevation (D1.02) were completed by the middle of May 2024.

Demolition was also completed by mid-May 2024 with the installation of footings, columns and block work for prop removal (Level 1 internal). Roof leaks were repaired above the stage.

Hoardings were installed where the windows had been removed. Load bearing walls were removed where required, with footings being exposed and geotechnical investigations undertaken to firm up footing design.

Demolition works at Lismore City Hall.

Restoration inside Lismore City Hall.

Restoration inside Lismore City Hall.