Lismore Municipal Building

August 2024 update

The Lismore Municipal Building saw significant progress with the completion of service rough-ins and the first concrete pour for the ground floor slab. Corbel repairs were well underway, enhancing the building's architectural integrity. Stair rectification efforts continued with notable progress, including the application of the first coat of stain. The framing around the main room's AC unit was finalized, ready for sheeting, as efforts to finish corbel detailing by Rofe Rendering were completed, ensuring the building's readiness for further interior development.

work inside the building.

July 2024 update

Work on the Municipal Building advanced with continued external parapet works.

Flooring demolition began to make way for the new concrete floor.

Render on architraves advanced and concrete pours for bathroom and foyer areas were completed.

Doorways were resized with new concrete lintels installed.

May 2024 update

During May 2024, the demolition of the corbel was well underway. As was rendering and the chasing for lights.

Towards the end of May 2024, the new timber floors on the first floor were being laid and the demolition of the kitchen in progress. Sand blasting of the main room was also in progress.

Works at the municipal building.

Inside the building during restoration.