Cawongla Road

Project Timeline

  • Project Status: Completed
  • Completion Date: January 2023

Works commenced in December 2022 on Cawongla Road to replace two two culverts that suffered significant damage during the 2022 natural disaster (AGRN1012).

The works consisted of replacing two culverts that suffered significant damage during the 2022 floods.

Excitingly, the works were completed ahead of schedule, opening in January 2023 before the local school returned to reduce any impact from the closure on local families and motorists.  

Cawongla Road Pipe Replacement Project