Eureka Road
During this busy month (August 2024) at the construction site, significant advancement has been made. The installation of the side track, driven steel piles, bridge abutments and rock scour protection is now complete. Towards the end of July, crews completed the bridge deck pour with concrete curing now underway. Following these tasks, the bridge approach works are scheduled to commence in early August.