Graham Road

Project Timeline

  • Project Status: Completed 
  • Completion Date: August 2024

Works commenced in April 2024 for installation of a new bridge on Graham Road. 

The previous box culvert was damaged during the 2020 natural disaster (AGRN943) and approval was obtained to replace the ineffective structure with a bridge system. 

These works involved removing the existing infrastructure and preparing the area for bridge construction. To minimise impact to residents and traffic flow during the construction work a temporary track was established as a side road.

Graham.jpg